Building Update
Progress to Date:
a. Installing main roof
b. Exterior stud framing west and south elevations
c. Exterior sheathing west and south elevations
d. Brick and mortar precast veneer installation north and west elevations
e. Interior wall framing Level 2
f. Duct installation ongoing Level 2
g. Mechanical, Electrical and Plumbing overhead ongoing Level 2
h. Fire protection piping Level 2
i. MEP in-wall rough-in Level 2
j. Completion of utility backfill within building pad
k. Slab-On-Grade (SOG) pours Line 5 to Line 12
l. Underslab rough-in Lines 1 to 4
m. Wall layout and overhead hanger installation started Level 1, Area B
n. Trap Primers - Mechanical Room
Two-Week Look Ahead:
a. Brick and precast installation north, west, and south - 40%
b. Aluminum window frame mockup installation - no glass
c. Roof installation to finish next week
d. Egress stair installation next week
e. Spray FP following roof installation completion
f. MEP in-wall rough-in Level 2
g. Final SOG pour Lines 1 to 4
h. Overhead MEP rough-in Level 1 ongoing
i. Interior walls toward west
j. Site utility subcontractor (Hampton Roads) to start next week