Building Update
Progress to Date:
- Installation of floor and roof Epic decking
- Completion of SOD deck pours at Level 2 and roof
- Begin mechanical curbs at roof
- Exterior stud framing and sheathing starting on southeast corner
- Interior wall layout Level 2
- Begin duct installation Level 2
- Mechanical, electrical and plumbing OH start Level 2
- Underslab rough-in at Mechanical and Electrical rooms and FP rises
- BCOM site visit
Two-Week Look Ahead:
- Continue exterior framing and sheathing
- Being air barrier installation
- Start brick flashing course
- Continue roof curbs
- Begin roof and window blocking
- Deliver roofing materials
- Begin Level 2 duct installation
- Continue SOG underslab rough-in
- SOG pour #1