Building Update

Progress to Date:

  • Installation of floor and roof Epic decking
  • Completion of SOD deck pours at Level 2 and roof
  • Begin mechanical curbs at roof
  • Exterior stud framing and sheathing starting on southeast corner
  • Interior wall layout Level 2
  • Begin duct installation Level 2
  • Mechanical, electrical and plumbing OH start Level 2
  • Underslab rough-in at Mechanical and Electrical rooms and FP rises
  • BCOM site visit

Two-Week Look Ahead:

  • Continue exterior framing and sheathing
  • Being air barrier installation
  • Start brick flashing course
  • Continue roof curbs
  • Begin roof and window blocking
  • Deliver roofing materials
  • Begin Level 2 duct installation
  • Continue SOG underslab rough-in
  • SOG pour #1

Site Navigation

Experience Guaranteed

Enhance your college career by gaining relevant experience with the skills and knowledge needed for your future career. Discover our experiential learning opportunities.

Academic Days

Picture yourself in the classroom, speak with professors in your major, and meet current students.

Upcoming Events

From sports games to concerts and lectures, join the ODU community at a variety of campus events.